Use case · material takeoff

From roof measurement to material order without retyping

A material order is only as good as the takeoff behind it. Each line on the order comes from a specific measurement: area drives shingles and underlayment, eaves and rakes drive drip edge and starter, ridges and hips drive cap.

Short answer

A roofing material takeoff converts measurements into purchasable quantities: sloped roof area plus waste becomes squares and bundles, eave and rake length becomes drip edge and starter, ridge and hip length becomes ridge cap, and valley length becomes valley material. Every quantity rounds up to whole units, because suppliers do not sell 2.3 bundles.

Which measurement drives which material

Coverage per unit varies by product, so always use the manufacturer's numbers. The relationships below are what a takeoff calculates.

Measurement to material mapping
MeasurementDrivesTypical unit
Sloped roof area plus wasteShingles, underlayment, nailsSquares, bundles, rolls
Eave lengthDrip edge, starter strip, ice and water barrierPieces, bundles, rolls
Rake lengthDrip edge, starter (if used on rakes)Pieces
Ridge and hip lengthRidge cap, ridge ventBundles, pieces
Valley lengthValley liner or ice and water barrierRolls
PenetrationsPipe boots, flashing kitsEach

Waste and rounding

Waste covers cuts at hips, valleys and edges. Simple gable roofs need less than cut-up hip roofs; many contractors use roughly 10 to 15 percent and adjust by complexity. Apply waste to area, then round each product up to the next whole unit you can buy.

Rounding at the end matters. Rounding every intermediate step up inflates the order; rounding down leaves the crew short on the roof.

Keeping the takeoff connected

In MeasureRoofNow the reviewed measurement feeds assemblies and your price book, and material quantities round up to whole purchasable units. If the measurement changes after the site visit, the quantities follow instead of being recalculated by hand.

Frequently asked questions

How many bundles are in a square?

Many asphalt shingles are packaged three bundles per square (100 sq ft), but some products differ. Check the coverage printed on the product.

Should waste be applied before or after rounding?

Apply waste to the measured area first, then convert to units and round up once at the end.

Can I use my own products and prices?

Yes. Each company sets up its own price book and assemblies.

Last reviewed October 25, 2026. Prices and product details change; check current terms before buying. This guide is not engineering, insurance, safety or construction advice.